Pprovision of FPSO Bunga Kertas Demobilisation Project

Marine & Engineering Consultancy Services for Bokor Betty Brownfield Rejuvenation

Client

PETRONAS CARIGALI / MISC Offshore Floating Terminals (L) Limited (MOFT)

Location

Penara-North Lukut Field, Offshore Terengganu

Commencement Date

May 2023 until Sept 2023

Project Background

Phase 1

  • Pre-survey prior FPSO Bunga Kertas decommissioning and as-left survey after complete demobilization
  • FPSO Bunga Kertas decommissioning, tow out from WORKSITE to Kuantan Port
  • Disconnection of four (4) sets of 180m length flexible risers (2 x12” production risers and 2 x 6” gas lift risers) from FPSO Bunga Kertas and wet store at WORKSITE (including preservation, subsea or marker buoy installation).
  • Disconnection of nine (9) lines of mooring chains (95mm dia x 350m length) from FPSO Bunga Kertas and wet store at WORKSITE (including subsea or marker buoy installation)

Phase 2

  • FPSO alongside at Kuantan Port
  • Removal of mooring chain & flexible riser pigtails from FPSO turret.
  • Tow out FPSO from Kuantan Port and deliver to MMHE Yard.

Challenges

  • Urgency of the project, prompt planning with careful evaluation to ensure delivery of the project safely within budget and a specific timeframe
  • FPSO Bunga Kertas is an ageing FPSO (38 years) that has been operating at Field for 19 years (as of 2023)