Project Background

Scope of Work

  • Provision of Detachment of FSO Duta Pacific
  • Provision of Hooking Up FSO Duta Pacific & Mooring Analysis
  • Provision of Procurement of the Mooring Accessories and Pressure & Leak Test of Buoy
  • Provision of Mobilization and Demobilization of Suitable Vessel(s)
  • Provision of Positioning & Site SurveyProvision of Disconnection and Reinstatement of 6” Manuli Hose

Deliverables

  • Project Management, Procurement, Onshore/Offshore Construction Team and all related engineering deliverables

Challenges

  • Urgency of the project, prompt planning with careful evaluation to ensure delivery of the project safely within budget and a specific timeframe
  • Offshore campaign for reinstatement was conducted during monsoon season.. Operating criteria have been developed which specify the length of the forecast period of stable weather prior to initiating the FSO mooring installation operation.